Project Description

The SLEX TR5 Alignment composes of eight (8) segments which will run parallel to the existing Philippine National Railway, Maharlika Highway and Padre Burgos National Road or Quirino Highway:

Segment Location Length (km)
Segment 1 Lucena to Gumaca, Quezon 61.00
Segment 2 Gumaca to Tagkawayan, Quezon 58.60
Segment 3 Tagkawayan to Sipocot, Camarines Sur 61.40
Segment 4 Sipocot to Naga City, Camarines Sur 39.50
Segment 5 Naga City to Polangui, Albay 45.90
Segment 6 Polangui to Legazpi City, Albay 33.60
Segment 7 Legazpi City to Sorsogon City, Sorsogon 57.70
Segment 8 Sorsogon City to Matnog, Sorsogon 62.30
Total 420.00

SLEX TR5, Segment 1 alignment starts at the termination point of the SLEX Phase II as the Toll Road 4 (TR4) Project at Brgy. Mayao, Lucena City, Quezon and ends at Gumaca, Quezon. The total length of Segment 1 is approximately 61 km. It will include four (4) interchanges (Pagbilao, Atimonan, Aglangan and Gumaca), as well as the toll plazas and operation center that will be necessary for the operation of Segment 1 thereof.

Supplemental Toll Operation Agreement (STOA)

Approved by the President of the Philippines on 27 June 2022.

Contracting Parties

Project Grantor: Toll Regulatory Board
Project Investor: South Luzon Toll Road 5 Expressway, Inc.
Project Operator: Manila Toll Expressway Systems, Inc.

Concession Period

30 years from the issuance of the Toll Operation Certificate (TOC).

Project Cost

Php 28.15 Billion [July 2021 prices] (Segment 1

Project Status

As of 05 March 2024:

  • On-going review of the Submitted Certified Final Engineering Design (FED) - Highway Drawings of Packages 1, 3, and 4.
  • The South Luzon TollRoad-5 Expressway, Inc. (SLTR5EI) submitted the Certified Final Engineering Design (FED) - Highway Drawings for Segment 1, Packages 1 (Lucena to Pagbilao, Quezon), 3 (Atimonan to Agdangan, Quezon), and 4 (Agdangan to Gumaca, Quezon).